The power plant is the collection of Click devices that provides power to the sensor and other Click devices. It provides surge protection and, if necessary, AC to DC power conversion (all Wavetronix devices run on DC power).
For installations supplied with AC power, the power plant includes the following:
For installations supplied with DC power, the power plant includes the following:
The most common way to obtain a power plant is to buy a preassembled backplate, of which the power plant will be part. In that case, the only setup that needs to be done is making sure that power is supplied to the backplate.
If you have purchased the individual components of the power plant, follow the steps in this document to assemble and install it.
If you have an installation with a traffic cabinet, the power plant will most likely be installed in there. If you’re just using a pole-mount box, no cabinet, that’s where the power plant should go.
Warning. An authorized electrical technician should install and operate these modules; there is a serious risk of electrical shock if the power source is handled unsafely.
The Click 210 is a compact circuit breaker, which will interrupt an electric current if there is an overload. After a current interruption, reset the breaker by pushing the reset button (on the front of the device).
Note. For ease in troubleshooting, we recommend you follow the wire color scheme outlined here.
Note. Terminal blocks 3 and 4 are directly bonded via the metal mounting foot of the base element to the DIN rail, so there’s no need for any additional grounding.
The Click 201 provides 1 A (enough to power one SmartSensor HD). The Click 202 provides 2 A, and the 204 provides 4 A. Choose accordingly. (If you’re using the Click 203, see that chapter in the Click 100-400 Series User Guide.)
Follow the steps below to get power from the Click 201/202/204 to the T-bus, the power and comms bus that powers the rest of the installation:
The Click 210 is a compact circuit breaker, which will interrupt an electric current if there is an overload. After a current interruption, reset the breaker by pushing the reset button (on the front of the device).
Note. For ease in troubleshooting, we recommend you follow the wire color scheme outlined here.
The power plant is the collection of Click devices that provides power to the sensor and other Click devices. It provides surge protection and, if necessary, AC to DC power conversion (all Wavetronix devices run on DC power).
For installations supplied with AC power, the power plant includes the following:
For installations supplied with DC power, the power plant includes the following:
The most common way to obtain a power plant is to buy a preassembled backplate, of which the power plant will be part. In that case, the only setup that needs to be done is making sure that power is supplied to the backplate.
If you have purchased the individual components of the power plant, follow the steps in this document to assemble and install it.
If you have an installation with a traffic cabinet, the power plant will most likely be installed in there. If you’re just using a pole-mount box, no cabinet, that’s where the power plant should go.
Warning. An authorized electrical technician should install and operate these modules; there is a serious risk of electrical shock if the power source is handled unsafely.
The Click 210 is a compact circuit breaker, which will interrupt an electric current if there is an overload. After a current interruption, reset the breaker by pushing the reset button (on the front of the device).
Note. For ease in troubleshooting, we recommend you follow the wire color scheme outlined here.
Note. Terminal blocks 3 and 4 are directly bonded via the metal mounting foot of the base element to the DIN rail, so there’s no need for any additional grounding.
The Click 201 provides 1 A (enough to power one SmartSensor HD). The Click 202 provides 2 A, and the 204 provides 4 A. Choose accordingly. (If you’re using the Click 203, see that chapter in the Click 100-400 Series User Guide.)
Follow the steps below to get power from the Click 201/202/204 to the T-bus, the power and comms bus that powers the rest of the installation:
The Click 210 is a compact circuit breaker, which will interrupt an electric current if there is an overload. After a current interruption, reset the breaker by pushing the reset button (on the front of the device).
Note. For ease in troubleshooting, we recommend you follow the wire color scheme outlined here.
The power plant is the collection of Click devices that provides power to the sensor and other Click devices. It provides surge protection and, if necessary, AC to DC power conversion (all Wavetronix devices run on DC power).
For installations supplied with AC power, the power plant includes the following:
For installations supplied with DC power, the power plant includes the following:
The most common way to obtain a power plant is to buy a preassembled backplate, of which the power plant will be part. In that case, the only setup that needs to be done is making sure that power is supplied to the backplate.
If you have purchased the individual components of the power plant, follow the steps in this document to assemble and install it.
If you have an installation with a traffic cabinet, the power plant will most likely be installed in there. If you’re just using a pole-mount box, no cabinet, that’s where the power plant should go.
Warning. An authorized electrical technician should install and operate these modules; there is a serious risk of electrical shock if the power source is handled unsafely.
The Click 210 is a compact circuit breaker, which will interrupt an electric current if there is an overload. After a current interruption, reset the breaker by pushing the reset button (on the front of the device).
Note. For ease in troubleshooting, we recommend you follow the wire color scheme outlined here.
Note. Terminal blocks 3 and 4 are directly bonded via the metal mounting foot of the base element to the DIN rail, so there’s no need for any additional grounding.
The Click 201 provides 1 A (enough to power one SmartSensor HD). The Click 202 provides 2 A, and the 204 provides 4 A. Choose accordingly. (If you’re using the Click 203, see that chapter in the Click 100-400 Series User Guide.)
Follow the steps below to get power from the Click 201/202/204 to the T-bus, the power and comms bus that powers the rest of the installation:
The Click 210 is a compact circuit breaker, which will interrupt an electric current if there is an overload. After a current interruption, reset the breaker by pushing the reset button (on the front of the device).
Note. For ease in troubleshooting, we recommend you follow the wire color scheme outlined here.
The power plant is the collection of Click devices that provides power to the sensor and other Click devices. It provides surge protection and, if necessary, AC to DC power conversion (all Wavetronix devices run on DC power).
For installations supplied with AC power, the power plant includes the following:
For installations supplied with DC power, the power plant includes the following:
The most common way to obtain a power plant is to buy a preassembled backplate, of which the power plant will be part. In that case, the only setup that needs to be done is making sure that power is supplied to the backplate.
If you have purchased the individual components of the power plant, follow the steps in this document to assemble and install it.
If you have an installation with a traffic cabinet, the power plant will most likely be installed in there. If you’re just using a pole-mount box, no cabinet, that’s where the power plant should go.
Warning. An authorized electrical technician should install and operate these modules; there is a serious risk of electrical shock if the power source is handled unsafely.
The Click 210 is a compact circuit breaker, which will interrupt an electric current if there is an overload. After a current interruption, reset the breaker by pushing the reset button (on the front of the device).
Note. For ease in troubleshooting, we recommend you follow the wire color scheme outlined here.
Note. Terminal blocks 3 and 4 are directly bonded via the metal mounting foot of the base element to the DIN rail, so there’s no need for any additional grounding.
The Click 201 provides 1 A (enough to power one SmartSensor HD). The Click 202 provides 2 A, and the 204 provides 4 A. Choose accordingly. (If you’re using the Click 203, see that chapter in the Click 100-400 Series User Guide.)
Follow the steps below to get power from the Click 201/202/204 to the T-bus, the power and comms bus that powers the rest of the installation:
The Click 210 is a compact circuit breaker, which will interrupt an electric current if there is an overload. After a current interruption, reset the breaker by pushing the reset button (on the front of the device).
Note. For ease in troubleshooting, we recommend you follow the wire color scheme outlined here.